Caboose Final Sign Off Scheduled

On
21 May 2008
, our backyard caboose, WP668
passed its first electrical inspection by the City of San Jose.
Last weekend, John added the exterior lights to WP668, the last big
electrical chore on his list. The final city inspection, of the electrical
and the stair rail, is scheduled for later this week. John and I started work
with the city on permits and variances in January 2007. I will be very happy
to have the permitting process finally complete!

WP668

WP668 Caboose, San Jose CA
photo: copyright 2008 Katy Dickinson
Work in progress on WP668:

  • This week:

    Final stairway and electrical inspection and sign off
  • Short term:
    • Attach Western Pacific decal to steel plate on side of WP668
    • Upgrade garden lighting around WP668
    • Paint touch up (base coat, trim, and markings)
    • Welding cleanup and metal coating for the stair railing
  • Longer term:
    • Install roof walk, attach it to existing ladders
    • Install bay window seat
    • Restore the rest of the windows (1 done, 5 to go)
    • Complete the back deck and step woodwork (steel is done)
    • Restore brake rigging and wheels
    • Reattach and restore battery box
    • Restore the doors

Leave a comment

Filed under Caboose Project and Other Trains

Leave a comment