WP668 Caboose Move Update

This week, we finally got the formal recommendation from our Civil Engineer with regard to securing the WP668 caboose for earthquake safety. His formal report (with an official Registered Professional Engineer seal and everything) gets submitted with John’s latest drawings to request the San Jose building permit. The drawings are of the steps and railing which will enclose the entry platform of the caboose, and the associated deck. John will go over to City Hall early next week. Once we have the building permit, we can schedule the crane for the caboose lift onto the wheels and track in our back yard.